This project had three phases: the 63,071 sq ft manufacturing phase addition, the 3,367 sq ft office phase addition, and the 1,094 sq ft receiving addition phase. The manufacturing addition was a new PEMB furnished by Nucor and included six new loading docks. The Office addition featured a new main entrance with an expanded break Room, a new lobby, a training Room, a conference Room, and locker rooms. The new Receiving area included three new interior offices and parts storage for maintenance.
Square feet
0
Project Type
New Building
Architect
BMA Architects
Completed
2018
Consumers Energy
Ludington Pumped Storage Plant
Ludington
This project included two phases for the South and North Fabrication shops. It included:
A sliding bi-parting doors
A insulated metal roof panel and wall panel system
Removable structural steel roof hatch
Overhead bridge crane
Square feet
0
by
Square feet
0
Project Type
New Building
Architect
Black and Veetch
Completed
2013
Howmet Alcoa Plants 3&4
Whitehall
This project consisted of two phases: Howmet Plant 3 and Howmet Plant 4. Both had unique challenges. Plant 3 needed to stay open during construction and Plant 4 required a large furnace pit that needed to be constructed before any foundation could be laid. Plant 3’s project scope included rerouting existing sewer lines, interior demolition, new loading docks, and new office space. Plant 4’s project scope included the installation of a 5-ton bridge crane and creation of a staging area, breakroom, technician room, and mezzanine.
We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.Ok